Support Our Heroes

The Vision Becoming Reality

Like in all construction projects, there are hurdles to overcome. See below the progress being made and join us to make it happen.

America for Veterans Foundation representatives walking the Veterans Village property

Ron Powers, Ron Fryer, and Mike Stacey walking the property. April 2016

2025 Groundbreaking with family and board members. June 2025

Trees being removed from the Veterans Village site before construction, March 2026

Trees being removed before construction. March 2026

Ron and Rosemary Fryer

The Founders featured in the Columbian. April 2026

Excavation started for Veterans Village

The location required oversized storm drainage pipes to be installed. The 14′ deep trench was excavated. April 2026

Stormwater pipes being laid at the Veterans Village site

Installing large underground pipes to provide reliable stormwater drainage. May 2026

Newly installed storm drain pipes covered with fill as backfilling continues at the Veterans Village site, June 2026

The newly installed storm drain pipes have been covered with fill, and the surrounding area is being backfilled as construction progresses across the site. June 2026

Excavated ground being backfilled and graded over the completed storm drain at the Veterans Village site, July 2026

The storm drain installation is complete in this area, and the excavated ground is being backfilled and graded to prepare the site for construction of Veterans Village. July 2026

Sewer pipes delivered for the Veterans Village construction project

Sewer pipes and fittings are delivered and staged for installation. August 2026

Second view of sewer line installation at the Veterans Village site

Sewer pipes and connections are assembled and installed in the excavated trench. September 2026

Sewer line and access connections installed at the Veterans Village site, September 2026

The sewer line and access connections are installed as the underground infrastructure nears completion. September 2026

Water line being rerouted at the Veterans Village site, September 2026

Required rerouting of water line. September 2026

Check back soon.